Drilling through the wall
Original ResinBau drawing · example at 45° and 50% thickness. The red mark indicates the dimension being discussed; the drawing does not change scale.
CALCULATOR · WALL-TO-FOUNDATION SLAB JOINT
Determine where to start drilling and how to reach the joint beneath the wall.
GEOMETRY · STRUCTURAL CROSS-SECTION
Change dimensions and observe the hole entry, joint intersection and additional depth.
Cross-section proportions change with the dimensions. It does not show reinforcement or the arrangement of hidden layers.
The foundation slab is shown schematically. The calculator does not know its thickness — check the available space for additional drilling. Geometric results may differ slightly from standard results, which use rounded coefficients.
TWO WAYS TO REACH THE SAME JOINT
Original ResinBau drawing · example at 45° and 50% thickness. The red mark indicates the dimension being discussed; the drawing does not change scale.
Original ResinBau drawing · example at 45° and 50% thickness. The packer passes through the floor layer and seals the hole in the wall.
Insert the packer through the floor so that the entire expanding rubber sleeve is inside the wall. Expand it only there — it must seal the hole in the wall, not in the floor layer. The blue outline in the drawing indicates the rubber sleeve.
The value indicates the packer's insertion depth into the hole. Insert it to this depth so that the entire expanding rubber sleeve is within the wall, beyond the floor layer, with room to expand correctly and seal the hole. Check the rubber sleeve position on the packer you use.
Total hole length = length to the joint + additional depth beyond the joint. The turquoise segment shows the extension along the hole; its length is illustrative and not to scale.
For a given angle, wall entry must be above the floor. If the calculated height is zero or negative, this option cannot be drilled above floor level. Check another angle or the option through the floor. A positive height still requires space for the drill and packer installation.
When drilling through the floor, the packer must reach the wall. Installing the rubber sleeve only in the floor layer does not ensure correct material delivery to the joint beneath the wall.
The standard formula adds 7 cm to the length through the floor layer: 5 cm + 2 cm, as in the previous calculator. The result indicates the packer's insertion depth into the hole. The addition allows the expanding rubber sleeve to sit within the wall beyond the floor layer, where it can expand correctly and seal the hole.
Material appearing at the next packer confirms communication. The floor does not then need to be removed solely to expose the joint. Do not confuse surface leakage with transfer between ports.
STEP 2 · SPACING ALONG THE JOINT
Position subsequent holes along the wall-to-foundation slab joint. Start with spacing equal to 50% of wall thickness. This is port spacing, not joint intersection depth or offset from the wall.
If material does not reach the next port, check that the joint is intersected, holes are clear and packers are correctly installed. If transfer is still not achieved, reduce the distance between successive holes.
If material readily reaches the next packer and you confirm filling of the joint section, consider wider spacing of subsequent holes — fewer packers per linear metre.
Leakage at the wall or from beneath the floor does not replace transfer to the next port. Check the joint closure and material escape route before increasing spacing.
STEP 3 · CHECK MATERIAL TRANSFER
In both options, material should reach the next packer. If a trial confirms this transfer, there is no need to remove the floor solely to expose the joint.
If material does not reach the next packer during the injection trial, we suggest cutting and locally removing a strip of floor beside the wall to expose the joint. This allows its face to be prepared and sealed before further injection. The procedure is described in the guide below.
Correct joint injection procedure — Knowledge guide →Actual layer arrangements and construction conditions may differ. Confirm dimensions and the method on site and through an injection trial.