Skip to content

CALCULATOR · WALL-TO-FOUNDATION SLAB JOINT

Construction joint drilling

Determine where to start drilling and how to reach the joint beneath the wall.

STRUCTURE DATA

Wall and floor

Full wall thickness above the joint, excluding finishing layers.

From the floor surface to the wall-to-foundation slab joint. If no additional floor layer has been cast over the foundation slab, enter 0 or leave blank. The foundation slab remains — the joint is still beneath the wall. Do not enter the foundation slab thickness.

Distance into the wall from the side you are drilling from.

Drilling angle

In the wall: angle from the vertical wall surface. In the floor: angle from the horizontal floor surface.

Additional length along the hole axis beyond the joint. You may enter your own value, including 0. It does not change the entry location or packer insertion depth.

TWO WAYS TO REACH THE SAME JOINT

Through the wall or through the floor?

01 / THINNER FLOOR LAYER

Drilling through the wall

Original ResinBau drawing · example at 45° and 50% thickness. The red mark indicates the dimension being discussed; the drawing does not change scale.

02 / THICKER FLOOR LAYER

Drilling through the floor

Original ResinBau drawing · example at 45° and 50% thickness. The packer passes through the floor layer and seals the hole in the wall.

How deep should the packer be inserted?

Insert the packer through the floor so that the entire expanding rubber sleeve is inside the wall. Expand it only there — it must seal the hole in the wall, not in the floor layer. The blue outline in the drawing indicates the rubber sleeve.

The value indicates the packer's insertion depth into the hole. Insert it to this depth so that the entire expanding rubber sleeve is within the wall, beyond the floor layer, with room to expand correctly and seal the hole. Check the rubber sleeve position on the packer you use.

Total hole length = length to the joint + additional depth beyond the joint. The turquoise segment shows the extension along the hole; its length is illustrative and not to scale.

01 / ENTRY SELECTION

When should you switch to the floor?

For a given angle, wall entry must be above the floor. If the calculated height is zero or negative, this option cannot be drilled above floor level. Check another angle or the option through the floor. A positive height still requires space for the drill and packer installation.

02 / PACKER INSTALLATION

Expanding rubber sleeve inside the wall

When drilling through the floor, the packer must reach the wall. Installing the rubber sleeve only in the floor layer does not ensure correct material delivery to the joint beneath the wall.

How is packer insertion depth calculated?

The standard formula adds 7 cm to the length through the floor layer: 5 cm + 2 cm, as in the previous calculator. The result indicates the packer's insertion depth into the hole. The addition allows the expanding rubber sleeve to sit within the wall beyond the floor layer, where it can expand correctly and seal the hole.

03 / INJECTION TRIAL

Check transfer to the next packer

Material appearing at the next packer confirms communication. The floor does not then need to be removed solely to expose the joint. Do not confuse surface leakage with transfer between ports.

Compare results for 30°, 45° and 60°

STEP 2 · SPACING ALONG THE JOINT

Where should the next hole be drilled?

Position subsequent holes along the wall-to-foundation slab joint. Start with spacing equal to 50% of wall thickness. This is port spacing, not joint intersection depth or offset from the wall.

No transfer? Reduce spacing

If material does not reach the next port, check that the joint is intersected, holes are clear and packers are correctly installed. If transfer is still not achieved, reduce the distance between successive holes.

Easy transfer to the next port

If material readily reaches the next packer and you confirm filling of the joint section, consider wider spacing of subsequent holes — fewer packers per linear metre.

Surface leakage is a different signal

Leakage at the wall or from beneath the floor does not replace transfer to the next port. Check the joint closure and material escape route before increasing spacing.

STEP 3 · CHECK MATERIAL TRANSFER

Thin and thick floor layers — the same injection objective

In both options, material should reach the next packer. If a trial confirms this transfer, there is no need to remove the floor solely to expose the joint.

Resin at the next packer
Thinner floor layer — entry through the wall
The hole reaches the joint beneath the wall, bypassing the floor layer. Resin appears at the next packer: communication is established.
Resin at the next packer
Thicker floor layer — entry through the floor
The packer passes through the floor layer, but the rubber sleeve seals the hole in the wall. Resin transfer to the next packer allows the floor to remain.

If material does not reach the next packer during the injection trial, we suggest cutting and locally removing a strip of floor beside the wall to expose the joint. This allows its face to be prepared and sealed before further injection. The procedure is described in the guide below.

Correct joint injection procedure — Knowledge guide →

Actual layer arrangements and construction conditions may differ. Confirm dimensions and the method on site and through an injection trial.