Voids, cracks and gaps
Concrete, reinforced concrete, masonry and stone within the thickness range stated in the TDS. Grain size and gap accessibility limit the ability to inject.
MINERAL VOID FILLING
Fine-grained injection mortar for filling gaps and voids in concrete, masonry and stone, including water-filled spaces — with flow under control.
| Product / preparation | Dry mortar + 3 l of water (±4%) per 15 kg |
|---|---|
| Filling thickness range | From 0.6 mm to 10 cm |
| Grain size | Up to 0.150 mm |
| Dry mix consumption | Approximately 1.45 kg per 1 l of fresh mortar |
| Working time at 20°C | 30 min |
| Application temperature | Material, ambient and substrate temperature +5 to +30°C |
| Delivery method | Injection mortar pump; manual, mechanical or gravity application possible |
Read values together with the temperature, material state and test conditions.
| Compressive strength after 1 / 7 / 28 days | 10 / 25 / 35 MPa |
|---|---|
| Flexural strength after 1 / 7 / 28 days | 2.0 / 3.7 / 5.6 MPa |
| Shrinkage after 90 days — PN-EN 12617-4 | ≤ 0.9 mm/m |
| Pull-off adhesion after 28 days | 1.5 MPa to a concrete substrate |
| Watertightness — PN-88/B-06250 | W12 |
| Water per 15 kg of dry mix | 3 l ±4%, i.e. 2.88–3.12 l |
1,45 kg/l describes dry mix consumption per litre of mortar, not the density of the entire wet mix. Mortar results do not determine anchor or repaired element capacity. Water conditions must protect the fresh filling from flow.
First establish the repair objective, substrate condition, presence of water and joint movement.
Concrete, reinforced concrete, masonry and stone within the thickness range stated in the TDS. Grain size and gap accessibility limit the ability to inject.
The mortar has increased resistance to washout. The TDS requires no flow during injection and for 12 h afterwards, depending on the element temperature.
Embedding anchors and bars in concrete or rock and stabilising pipes within the scope specified by the design. This does not replace selection of anchorage length and capacity.
Standing water and active flow are different conditions. Do not inject fresh mortar into an uncontrolled stream. Do not treat rigid mortar as a flexible seal for a moving joint. Protect fresh filling from drying and frost.
Water-filled voids permitted; no flow during application and for 12 h afterwards, depending on temperature. Rigid filling; not intended to accommodate expansion joint movement.
Dry mix + water
Mortar pump or gravity application
Mineral, rigid filling
Work sequence after assessing the structure and selecting the method. Full requirements are given in the product instructions.
Check voids, accessibility and access routes. For water-filled spaces, plan to stop the flow during delivery and curing.
Pour water into a clean container. Add dry mortar while mixing. For 15 kg, use 3 l ±4% of water.
Do not substitute trowel mixing for the recommended mixing method. Match the batch to the working time and apply using equipment intended for mortar.
Monitor material passage and quantity. Protect the mortar from washout, frost and rapid drying. Clean tools and the system with water according to the pump instructions.
Choose the instructions for your task and calculate material quantities using clearly defined assumptions.
Data, application instructions and safety documents for the supplied material.
Before use, read the current documentation for all supplied components. Select protective equipment, ventilation and cleaning methods appropriate to the material and equipment.
Prepare a description of the substrate, water, geometry and expected result. Let us select the material and delivery method.