MASONRY-TO-SLAB JOINT · SEALING
Old masonry, new slab.
Water at the joint.
After the basement was deepened, a new slab met the existing masonry. Sealing required assessment of the cross-section, control of inflow and preparation of access to the joint.
01 · PROBLEM AND ASSESSMENT
Waterproof slab.
Leaking joint.
During refurbishment, the basement was deepened and a new waterproof concrete slab was constructed. The old brick walls remained supported on footings. Their junction with the new slab received no additional sealing. At high groundwater levels and after heavy rainfall, water appeared at the joint, periodically flooding the rooms.
Incomplete documentation and earlier alterations made the cross-section difficult to interpret. Exploratory holes revealed voids in the masonry. Removing a floor strip and pumping out water exposed the repair zone and revealed the actual inflow locations.
02 · DECISIONS AND WORK SEQUENCE
Each stage had a defined task
Substrate preparation, reduction of active flow and main injection formed a single repair sequence.
- 01 / PREPARATION
Exposure and closure of defects
Visible brick and mortar joint defects were initially closed with rapid-setting mortar. Holes were drilled through the slab towards the masonry, and packers were installed.
CrackOn.5 → - 02 / PRELIMINARY INJECTION
Controlling inflow and voids
WaterStopper was injected into the joint zone and masonry voids. Local seepage remained after this stage — reduced inflow allowed work to continue.
WaterStopper → - 03 / MAIN INJECTION
Sealing the remaining water paths
HydroGum was used in the second stage. Pressure and material consumption were monitored during injection, adapting delivery to the structure's behaviour.
HydroGum → - 04 / FUTURE ACCESS
Preparing for further intervention
After injection and before floor reinstatement, hoses were laid for potential future work. Limited access and possible changes in ground and water conditions were taken into account.
ACCESS AFTER THE REPAIR
Hoses prepared for future intervention
Hoses were laid after the main HydroGum injection and before floor reinstatement. They provided prepared access for possible later material delivery.
Injection hoses — planning access →03 · RESULT AND LESSON
Joint assessment determines the repair scope
Watertightness achieved, as reported by the author
Piotr Kobus reports complete watertightness after the main injection. The waterproof concrete floor layer was then reinstated, allowing room refurbishment to continue.
The water resistance of a new slab alone does not ensure a watertight junction with old masonry. In this case, the solution also addressed voids, inflow paths and access after refurbishment. This scope must be considered when planning the method.
Source: Piotr Kobus, “Reverse Joint Context”, Injection(s) Case Studies, pp. 37–44. Adapted from the author's case study of ResinBau product applications.
CASE RECORD
From inflow assessment to floor reinstatement
A similar problem at your site?
Let's assess the cross-section, water paths and access to the sealing zone.
